uccess in a plant stoppage project implies the rigorous meeting of deadlines of a time chart by a qualified and trained team. EKIPE-C offers to each of its valued customers the assurance that springs out of the experience in having done substantial large industrial and public works renovation projects in time or ahead according to schedule.
Case: Plant Stoppage

Customer: Siderar / Techint
Location: Steel Mill at San Nicolas - Argentina
Job: Quenching  Tower  II - Coke Plant
Job Description : Controlled Demolition of concrete tower to quench coke carried by railcars.
Size: 30 meters high; 155m ² diamond wire sawn.
Ekipe-C: Cutting and removal of 20 ton ave. weight pieces, being the heaviest of 90 tons.

dutoReasons for specifying Controlled Demolition: A smoke duct in concrete with refractory inner lining under the structure to be demolished precluded any impact or vibration that might interrupt the exhaust due to collapse. Time was also a determining factor, since while this "chimney" was disassembled, a sole Quenching Tower had to process all coke production for the Steel Mill. EKIPE-C's  job completion time was 13 days.

Some Customers



Job Gallery

Galeria de Trabalhos
Photo Gallery

Contact Online

Enquete

O que você achou do nosso novo site?
 

Login Area Manager



banner_expereiencia_en

EXPERIENCE

"LEADER IN CONTROLLED DEMOLITION"

PLANNING

"HIGHLY QUALIFIED TECHNICAL STAFF"

PUNCTUALITY

"COMPANY RECOGNIZED AND HIGHLY REGARDED IN THE MARKET"